Project · Nut hulling and shelling

Shelling Plant Modernization, Season by Season

Rows of Eaton motor starters linked by SmartWire-DT ribbon cable inside a nut sheller MCC built by PCA

Industry: A Central Valley almond huller and sheller (delivered with an electrical contractor)

The challenge

The plant’s sheller ran on an SLC 500, and the owner added equipment almost every year: new color sorters, a new huller line and precleaner changes. Each addition brought new motors and a new plant start sequence.

What we did

  • Replaced the SLC 500 processor with an Allen-Bradley CompactLogix and converted the sheller program, keeping the existing SLC I/O rack in service as remote I/O over EtherNet/IP. Designed a new sheller control panel and remote I/O panel, added an Ignition HMI and set up eWON remote access.
  • For a new sorting line and huller, designed new Eaton SmartWire-DT MCCs, a baghouse panel and remote I/O panels for the bins, with an ABB soft starter on EtherNet/IP and a C-more bin conveyor HMI.
  • Moved the plant start sequence into SQL tables in Ignition (motors, start sequence and systems), so new equipment is added as data rather than new screens and code.
  • Added a precleaner remote I/O panel and rebuilt the master start sequence; later programmed a CLICK PLC and C-more HMI for a sort line and rolled out a new plant start sequence for another season.

The result

A mixed Allen-Bradley, AutomationDirect and Ignition plant that grows each harvest without starting over, with PCA returning season after season.

Platforms and equipment

Allen-Bradley SLC 500 to CompactLogix, Eaton SmartWire-DT, ABB soft starter, Ignition with SQL, AutomationDirect CLICK and C-more, eWON

Related

Have a similar project?

Tell us what you are working on through the quote request form or the contact page. We design, build, program and start up control systems for plants across California.

Have a panel or project in mind?

Answer a few quick questions and a PCA engineer will get back to you within one business day.