Project · Manufacturing and transit equipment

Synchronized Rail-Car Lifting Jack Controls

Mobile main control console with Siemens touch panel and E-stop for synchronized rail-car lifting jacks, built by PCA

Industry: Rail transit maintenance equipment, delivered for an equipment manufacturer to a transit agency in Washington

The challenge

An equipment manufacturer supplying eight portable 10-ton lifting jacks to a light-rail maintenance facility needed a control system that lifts a vehicle with the jacks in sync and protects against uneven lifts and over-travel.

What we did

  • Engineered and built the main mobile control panel, plus a junction box and local control box for each of the eight jacks, connected with plug-in cables and hard-wired safety interlocks.
  • Programmed a Siemens S7-1200 PLC and a Siemens touch panel with single-jack mode and group lift/lower of four or eight jacks, synchronization monitoring, limit and proximity switches for load contact and travel limits, and password-protected mode changes.
  • Wrote the description of operation and delivered the drawings and nameplates.
  • Commissioned the system on site at the transit agency’s facility in Washington.

The result

A synchronized lifting system for loads up to 80 tons, commissioned on site out of state on a Siemens platform.

Platforms and equipment

Siemens S7-1200, Siemens touch panel HMI

Related

Have a similar project?

Tell us what you are working on through the quote request form or the contact page. We design, build, program and start up control systems for plants across California.

Have a panel or project in mind?

Answer a few quick questions and a PCA engineer will get back to you within one business day.